#98 - Case History - How Did That Get There?
August 18th, 2026
17 mins 54 secs
Your Hosts
Tags
About this Episode
GBA Case History Series – Case History #98 - How Did That Get There?
Summary
Member Firm provides geotechnical engineering services and CoMET for a new project on the site of an existing shopping center. CoMET services were provided “as needed” for demolition of the shopping center. A few years after the completion of construction, one of the three new retaining walls deflected significantly. Investigation of the backfill led to some surprises. On cue, the owner sued to reclaim the repair costs
Our Hosts:
- Elizabeth Brown, PE - Principal Geotechnical Engineer/JLT Consultants
Elizabeth is the Principal Geotechnical Engineer at JLT Consultants in Boise, Idaho. Elizabeth has performed and/or assisted with numerous geotechnical investigations throughout Idaho, Oregon, Washington, and Wyoming managing projects, providing geotechnical design, project quality control, cost and value engineering, and evaluating geotechnical constructability issues.
- Abi Corbett – Project Consultant/SME.
Abi is a Project Consultant at SME experienced in managing a variety of steel, concrete, coatings, and nondestructive testing projects. She specializes in managing projects related to DOT fabrication quality assurance reviews but also supports project managers throughout SME’s various service groups.
Lessons Learned:
- Beyond the Go/No-go Analysis
- Quality Assurance Is Not Quality Control
- Defining Terms Is Essential
- No Good Deed Goes Unpunished
- Spot-checking Elevates Risk
- Reusing Existing Materials May Create Special Risks
- Constructors May Not Implement Adequate QC
- Effective CoMET Documentation Describes What Was and Was Not Observed
- Communication at All Levels Can Be Critical
- Rely on Experienced Legal Guidance
- “Agreeable” Experts Are Always Available
- Claims Are a Business Issue
- Alternative Dispute Resolution Works
Calls-to-action:
- Download Case History #98
- Visit the following link to access all of GBA’s Case Histories: https://www.geoprofessional.org/gba-case-histories/
- An account is required to download the individual Case Histories, which are free for GBA Member Firms.
- Visit the GBA Website at https://www.geoprofessional.org for other training resources and reference materials and/or to become a member.
- Visit https://www.gbapodcast.com for future Podcast Episodes
- Contact us at info@geoprofessional.org with any podcast-related questions or comments
Subscribe
- Subscribe to the GBA Podcast https://www.gbapodcast.com/subscribe
This episode was produced by the following GBA Members:
- Abi Corbett – Project Consultant/SME.
- Elizabeth Brown, PE - Principal Geotechnical Engineer/JLT Consultants
- Ryan White, PE, GE – Principal Geotechnical Engineer/Apex Companies, LLC
Transcript
Case History 98
Liz
Welcome to the GBA Case History Series, brought to you by the GBA Podcast. My name is Elizabeth Brown, and I'm a principal geotechnical engineer at JLT Consultants.
Abi
And I'm Abi Corbett, a project consultant at SME. So today's episode is a wild ride. We're talking about a shopping center redevelopment project that has everything: old fill, big box tenants, tight schedules, reused materials, a contractor with, let's call it creative quality control, and a phrase that should haunt every engineer's dream, "As needed."
Liz
So if you've ever wondered how two words can cost a firm 50 grand and years of stress, buckle up, 'cause today we're diving into case history number 98.
Read Full Transcript Hide Full Transcript
Abi
Okay, picture this. A national shopping center owner wants to demolish 75% of a 35-year-old mall and rebuild it as a shiny new retail center. Big project, big tenants, big schedule pressure.
Liz
And the site? Well, it's 60-plus acres of old fill. They're gonna have some new cuts, new fills, three retaining walls up to 25 feet tall. Two of those walls are gonna support, like, these big box buildings. So I mean, really, this, it's not medium risk. This is, you know, like, CEO gets involved type of risk.
Abi
Right, and that's actually exactly what happened. The member firm CEO oversaw the proposal because the risks really were that high.
Liz
And then the owner ignored the firm's contract and sent their own, which did not contain a limitation of liability. So the CEO pushed back and eventually they negotiated a $1 million limitation if the firm also provided the CoMET services.
Abi
And here's where some trouble is gonna start. The contract said CoMET services would be provided as needed. No one defined it, not the owner, not the construction manager, not the geotechnical firm.
Liz
Oof. That phrase becomes the ghost that ends up haunting this entire project
Abi
And it leads us to our first big lesson. A go, no-go analysis isn't enough. So they identified some risks pretty early. That's why they got the CEO involved. But once they said go, they didn't follow through with that same rigor. The risk management thing, it's a process, not just a checkbox.
Liz
Exactly. And if you know a project is high risk, you can't afford vague language. You need clarity and documentation and communication at every step. So I mean, that as needed really should have been further defined.
Abi
Yes, 100% agree. Okay, so construction begins and the owner hires an excavation contractor known for being, quote, "bottom line focused." And by that, we mean one of their managers bragged about burying unsuitable materials when no one was watching
Liz
Oh yeah. Everybody knows that kind of contractor, and I think if you've been in the industry for any amount of time, everyone knows who that contractor is, unfortunately. So I mean, that's the kind of thing that really makes geotechnical engineers, wake up at 3:00 AM in a cold sweat.
Abi
Yeah. Definitely to say the least on that one. And the member firm assigned a senior principal and an experienced field rep to oversee construction. But the owner didn't just give them a blank check, so the team had to constantly decide what they're gonna observe and what they just basically have to skip.
Liz
Right. So I mean, I think a positive note here is that the firm recognized the risk, right? And so they made sure that they did have, a senior principal and that experienced field rep, right? They weren't putting the one-year-outta-school guy out of there, right? They made sure, "Hey, we're gonna get, some good quality people out on this site." And really here's where another lesson comes in, is that QA is not QC. So the CoMET firms provide quality assurance, not quality control. They're not the contractor's police force. But if the owner or contractor thinks that you're doing QC, you're already in trouble
Abi
Yeah, that's something I like to really get out in the open first thing in forefront with my projects is like very clearly say that QC is responsible for QC. I am just spot checking.
Liz
Right
Abi
And in this case, because no one defined as-needed, the field rep had to make judgment calls. He decided the cantilevered retaining wall, the one that's supporting landscaping, it, it was low priority. He skipped density testing and only did two spot checks.
Liz
I get his field judgment, right? It was a lower priority item, less risk to, life and limb type issues there. But really this kind of leads to another one of our lessons is that spot checking elevates risk. Spot checking assumes that the contractor is honest and consistent, but this contractor had a history of cutting corners.
Abi
Yeah. And there's a kicker. Pulverized asphalt and clay look similar from a distance. So reusing materials is great, environmentally friendly, cost-effective, but it creates opportunities for confusion or maybe even cheating.
Liz
Which kind of leads us to another lesson is that reused materials require heightened observation. There's so many different things that could happen or go wrong or, you know, blending of materials or things of that nature. So if the client declines that level of observation, right, that heightened observation, then really that needs to be documented, and to document it, I mean in writing, right? Like every single time.
Abi
Yeah. Like high, high, high focus on it. But the project finished, everyone celebrated, grand opening, smiles, break out the champagne.
Liz
Oh, yeah. But then, dun, dun, dun, the wall moved.
Abi
Right. A few years later, the property manager calls and quote, "One of the retaining walls is failing. Come figure it out." End quote.
Liz
So a 100-foot stretch had deflected. The keyways between the segments had sheared, and really the initial suspicion was hydrostatic pressure from a clogged drain
Abi
But when they drilled borings and installed groundwater monitoring wells, they found something much worse.
Liz
Yeah, unfortunately there was clay in the backfill. So what they found was alternating layers of pulverized asphalt and clay, even though clay was explicitly prohibited.
Abi
Contractor cheated. And because the field rep wasn't, I really couldn't watch that wall very closely. No one caught it.
Liz
Right. And so here's another lesson is the, the constructors may not implement adequate QC, like even the good ones. I mean, with schedule pressure, cost pressure, or just plain habit can lead to bad decisions.
Abi
Yeah, especially if you're feeling like it's a status quo kind of job. So the owner does need the wall fixed before they wanna sell the property. They set a $300,000 budget, hired a contractor, and the member firm did CoMET for this repair.
Liz
And based on those observations, the firm concluded that, hey, improper backfill was the primary cause of failure.
Abi
So here comes the lawsuit. First, the excavator and construction manager, and then the member firm.
Liz
Well, and as usual, right, with the lawsuits, everyone's pointing fingers at everybody else, right? The construction manager said, "Not our fault." And the excavator said, "We did what the geotechnical engineer told us." They even claimed that the member firm had someone on site, quote, "At all times."
Abi
Which is just absolutely false.
Liz
Right. So the member firm argued, number one, "Hey, they can't be everywhere at once." Number two, "They weren't required to observe everything." Number three, "The owner knew the CoMET scope was limited." And number four, "The contractor was responsible for meeting specs regardless of observation."
Abi
And here's a huge lesson. Effective documentation must describe what was not observed. Silence implies oversight, and oversight implies responsibility.
Liz
Right. So experts weighed in. One blamed clay, one said the distress was cosmetic, one blamed the wall design. Nobody agreed.
Abi
Imagine that. Which, I mean, it brings us to just another lesson. Agreeable experts are always available. Some experts really will say anything for the right fee. Their testimony can get kind of muddy and maybe even prolong a dispute.
Liz
Right. So in this case, the parties went to mediation, right? "Hey, let's get this settled out." And here's where another lesson hits hard is that litigation is not about truth, it's about persuasion. You need experienced construction claims attorneys who understand how to defend technical professionals.
Abi
Right. And the mediator's goal here wasn't to find who was right. It was to find a settlement everyone hated equally. So the excavator ended up paying $115,000. Our member firm paid 22,500, and the owner reduced its claim by $150,000.
Liz
Whew. And the member firm spent about $50,000 total, including unbilled time
Abi
Billed time is always such a big kicker
Liz
It is
Abi
All right, let's run back on all those lessons that we talked about throughout the case.
Liz
All right, so lesson one is risk management doesn't stop at go/no go. If you identify a project as high risk, you need heightened communication, documentation, and clarity throughout the entire project.
Abi
Big emphasis on entire.
Liz
Right.
Abi
All right, lesson two, QA is not QC. If an owner or a contractor thinks in any way you're doing QC, you are in trouble. We need to educate these people early and often that QA is not QC.
Liz
Right. And really by doing that, you're really helping to elevate the geoprofession as a whole. Like educating is to, you know, the proper way there. So lesson three, define your terms, especially quote, "As needed." So ambiguity is a liability magnet. If you don't define it, a lawyer will, and more than likely it won't be in your favor.
Abi
Ew. And look, lesson number four, no good deed goes unpunished. If you're trying to save a a client money by reducing your observation, it can backfire unless a client is explicitly approving it in writing.
Liz
Right. Writing is key. You want everything in writing. So lesson five, spot checking increases risk. If you're not there full-time, you must document what you did not see.
Abi
Lesson number six: reuse materials require vigilance. Pulverized asphalt looks like soil. Clay looks like soil. Cheating is just kind of easy in this case.
Liz
Agreed. Lesson seven: contractors may not implement adequate QC. Even honest contractors make mistakes. Some make choices.
Abi
Human element.
Liz
Great
Abi
Lesson eight: documentation must include what was not observed. Daily reports need to reflect reality, not just optimism.
Liz
And lesson nine, communication is everything. Weekly check-ins aren't enough on a complex project.
Abi
One of my favorite lessons, number 10, litigation is brutal. Opposing counsel is going to twist facts and you're going to need strong legal guidance
Liz
And building that relationship early with your legal counsel is a great idea. So lesson 11, experts can be bought. Prepare for testimony that contradicts reality
Abi
Lesson 12: claims are business decisions. A lot of times settling is just gonna be cheaper rather than fighting the fight and winning
Liz
Right. It's all about risk management there. So lesson 13, mediation works even if it feels unfair. It's about closure, not justice. As the CEO said, it can feel like, quote, "legal thievery," but it's cheaper than trial
Abi
I like the way that he put that.
Liz
Right
Abi
So that's about it for case history number 98, a perfect storm of unclear scope, reused materials, contractor shortcuts, and assumptions that went unspoken.
Liz
If you take nothing else away, let it be this. Define your scope in writing every time.
Abi
Thanks for joining us. Share this episode with anyone who's had to explain the difference between QA and QC.
Liz
And that concludes this episode of the Case History series brought to you by the GBA podcast. I hope you were able to take away some useful information that will help you and others at your firm make good risk-based decisions in the future. If this episode resonated with you or if you have a potential case history, we want to hear your story. Email us at info@geoprofessional.org or comment on our LinkedIn post.